Consider the Table Below with Information Regarding Each Activity, Immediate

question 33

Essay

Consider the table below with information regarding each activity, immediate predecessors, and duration estimates (in minutes) for each activity.  Activity  Immediate  Predecessors  Minimum  Time  Likely Time  Maximum  Time  A 679 B 4911 C  A 3912 D  B 2612 E  B, C 3510 F  D 479 G  E 4715\begin{array} { c | c | c | c | c } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessors }\end{array} & \begin{array} { c } \text { Minimum } \\\text { Time }\end{array} & \text { Likely Time } & \begin{array} { c } \text { Maximum } \\\text { Time }\end{array} \\\hline \text { A } & - & 6 & 7 & 9 \\\text { B } & - & 4 & 9 & 11 \\\text { C } & \text { A } & 3 & 9 & 12 \\\text { D } & \text { B } & 2 & 6 & 12 \\\text { E } & \text { B, C } & 3 & 5 & 10 \\\text { F } & \text { D } & 4 & 7 & 9 \\\text { G } & \text { E } & 4 & 7 & 15\end{array}  Consider the table below with information regarding each activity, immediate predecessors, and duration estimates (in minutes) for each activity.  \begin{array} { c | c | c | c | c }  \hline \text { Activity } & \begin{array} { c }  \text { Immediate } \\ \text { Predecessors } \end{array} & \begin{array} { c }  \text { Minimum } \\ \text { Time } \end{array} & \text { Likely Time } & \begin{array} { c }  \text { Maximum } \\ \text { Time } \end{array} \\ \hline \text { A } & - & 6 & 7 & 9 \\ \text { B } & - & 4 & 9 & 11 \\ \text { C } & \text { A } & 3 & 9 & 12 \\ \text { D } & \text { B } & 2 & 6 & 12 \\ \text { E } & \text { B, C } & 3 & 5 & 10 \\ \text { F } & \text { D } & 4 & 7 & 9 \\ \text { G } & \text { E } & 4 & 7 & 15 \end{array}     a. Using the PERT distribution in ASP to represent the duration of each activity, construct a simulation model to compute the total time to complete the task. b. What is the expected duration of the entire project? What is the standard deviation of the project duration? c. What is the likelihood that the project will be complete in 26 minutes?
a. Using the PERT distribution in ASP to represent the duration of each activity, construct a simulation model to compute the total time to complete the task.
b. What is the expected duration of the entire project? What is the standard deviation of the project duration?
c. What is the likelihood that the project will be complete in 26 minutes?


Definitions:

Proposition

A statement or assertion that expresses a judgement or opinion.

Predicate

A grammatical and logical component of a sentence that tells something about the subject, including a verb and possibly other components such as objects.

Proposition

A declaration that conveys an assessment or viewpoint, which may be accurate or inaccurate.

Predicate

A term used in logic to refer to the part of a sentence that tells something about the subject or presents an action, often represented after the subject.

Related Questions