A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below.  A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below.    \begin{array} { | c | c | c | c | c | c | c | c | c | c }  \hline \text { Activity } & \begin{array} { c }  \text { Immediate } \\ \text { Predecessors } \end{array} & \begin{array} { c }  \text { Activity } \\ \text { Time (weeks)} \end{array} & E S & L S & E F & L F & \text { Sack } & \begin{array} { c }  \text { Critical } \\ \text { Path? } \end{array} \\ \hline \mathrm { A } & & & & & & & & \\ \hline \mathrm { B } & & & & & & & & \\ \hline \mathrm { C } & & & & & & & & \\ \hline \mathrm { D } & & & & & & & & \\ \hline \mathrm { E } & & & & & & & & \\ \hline \mathrm { F } & & & & & & & & \\ \hline \mathrm { G } & & & & & & & & \\ \hline \mathrm { H } & & & & & & & & \\ \hline \end{array}  Now assume that the times listed are only the expected times instead of being fixed times. Is the probability of being finished in fewer than 25 weeks more or less than 50%?  Activity  Immediate  Predecessors  Activity  Time (weeks)ESLSEFLF Sack  Critical  Path? ABCDEFGH\begin{array} { | c | c | c | c | c | c | c | c | c | c } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessors }\end{array} & \begin{array} { c } \text { Activity } \\\text { Time (weeks)}\end{array} & E S & L S & E F & L F & \text { Sack } & \begin{array} { c } \text { Critical } \\\text { Path? }\end{array} \\\hline \mathrm { A } & & & & & & & & \\\hline \mathrm { B } & & & & & & & & \\\hline \mathrm { C } & & & & & & & & \\\hline \mathrm { D } & & & & & & & & \\\hline \mathrm { E } & & & & & & & & \\\hline \mathrm { F } & & & & & & & & \\\hline \mathrm { G } & & & & & & & & \\\hline \mathrm { H } & & & & & & & & \\\hline\end{array} Now assume that the times listed are only the expected times instead of being fixed times. Is the probability of being finished in fewer than 25 weeks more or less than 50%?


Definitions:

Plaintiff's Claim

A plaintiff's claim is a formal accusation or allegation made in a court by the plaintiff, starting legal proceedings against the defendant.

Tort

A legal wrong or infringement of a right leading to civil legal liability.

Nuisance

An act, condition, or thing that is considered an inconvenience or annoyance, and can sometimes give rise to a legal claim.

Bank's Carelessness

Negligent or inattentive actions by a banking institution that lead to loss or damage for a customer.

Related Questions