Dobson Construction Specializes in the Construction of Commercial and Industrial

question 6

Essay

Dobson Construction specializes in the construction of commercial and industrial buildings. The contractor is experienced in bidding long-term construction projects of this type, with the typical project lasting fifteen to twenty-four months. The contractor uses the percentage-of-completion method of revenue recognition since, given the characteristics of the contractor's business and contracts, it is the most appropriate method. Progress toward completion is measured on a cost-to-cost basis. Dobson began work on a lump-sum contract at the beginning of 2015. As bid, the statistics were as follows: Dobson Construction specializes in the construction of commercial and industrial buildings. The contractor is experienced in bidding long-term construction projects of this type, with the typical project lasting fifteen to twenty-four months. The contractor uses the percentage-of-completion method of revenue recognition since, given the characteristics of the contractor's business and contracts, it is the most appropriate method. Progress toward completion is measured on a cost-to-cost basis. Dobson began work on a lump-sum contract at the beginning of 2015. As bid, the statistics were as follows:   At the end of the first year, the following was the status of the contract:   It should be noted that included in the above costs incurred to date were standard electrical and mechanical materials stored on the job site, but not yet installed, costing $105,000. These costs should not be considered in the costs incurred to date. Instructions (a) Compute the percentage of completion on the contract at the end of 2015. (b) Indicate the amount of gross profit that would be reported on this contract at the end of 2015. (c) Make the journal entry to record the income (loss) for 2015 on Dobson's books.(d) Indicate the account(s) and the amount(s) that would be shown on the balance sheet of Dobson Construction at the end of 2015 related to its construction accounts. Also indicate where these items would be classified on the balance sheet. Billings collected during the year amounted to $1,900,000.(e) Assume the latest forecast on total costs at the end of 2015 was $4,060,000. How much income (loss) would Dobson report for the year 2015? At the end of the first year, the following was the status of the contract: Dobson Construction specializes in the construction of commercial and industrial buildings. The contractor is experienced in bidding long-term construction projects of this type, with the typical project lasting fifteen to twenty-four months. The contractor uses the percentage-of-completion method of revenue recognition since, given the characteristics of the contractor's business and contracts, it is the most appropriate method. Progress toward completion is measured on a cost-to-cost basis. Dobson began work on a lump-sum contract at the beginning of 2015. As bid, the statistics were as follows:   At the end of the first year, the following was the status of the contract:   It should be noted that included in the above costs incurred to date were standard electrical and mechanical materials stored on the job site, but not yet installed, costing $105,000. These costs should not be considered in the costs incurred to date. Instructions (a) Compute the percentage of completion on the contract at the end of 2015. (b) Indicate the amount of gross profit that would be reported on this contract at the end of 2015. (c) Make the journal entry to record the income (loss) for 2015 on Dobson's books.(d) Indicate the account(s) and the amount(s) that would be shown on the balance sheet of Dobson Construction at the end of 2015 related to its construction accounts. Also indicate where these items would be classified on the balance sheet. Billings collected during the year amounted to $1,900,000.(e) Assume the latest forecast on total costs at the end of 2015 was $4,060,000. How much income (loss) would Dobson report for the year 2015? It should be noted that included in the above costs incurred to date were standard electrical and mechanical materials stored on the job site, but not yet installed, costing $105,000. These costs should not be considered in the costs incurred to date.
Instructions
(a) Compute the percentage of completion on the contract at the end of 2015.
(b) Indicate the amount of gross profit that would be reported on this contract at the end of 2015.
(c) Make the journal entry to record the income (loss) for 2015 on Dobson's books.(d) Indicate the account(s) and the amount(s) that would be shown on the balance sheet of Dobson Construction at the end of 2015 related to its construction accounts. Also indicate where these items would be classified on the balance sheet. Billings collected during the year amounted to $1,900,000.(e) Assume the latest forecast on total costs at the end of 2015 was $4,060,000. How much income (loss) would Dobson report for the year 2015?

Determine the traits and skills relevant for relations-oriented leadership.
Analyze the benefits and potential risks of collective identification within teams or groups.
Identify the aspects of leadership that have been the focus of extensive research.
Understand the principles of effective learning environments and patient teaching methods.

Definitions:

Violation of Expectations

A cognitive development research method where infants are shown an event that defies their understanding, measuring their surprise to infer cognitive abilities.

Information-processing Ability

The capacity of the brain to analyze, evaluate, and retain information, helping in decision-making and problem-solving.

Causality

The relationship between cause and effect, where one event (the cause) directly influences the outcome of another event (the effect).

Innate Learning

Refers to the natural capability to understand and process information from birth, suggesting some knowledge or skills are not acquired but inherent.

Related Questions