Hydro One Plans to Complete a Modification with the Project

question 21

Essay

Hydro One plans to complete a modification with the project start date of March 12. The procurement activities begin on July 6 worth $3.5 million. Calculate the amount the project manager obtains on March 12 to pay for all the procurement, if money is worth 2.5% per year