Conflicts Between Two Mutually Exclusive Projects, Where the NPV Method

question 15

True/False

Conflicts between two mutually exclusive projects, where the NPV method chooses one project but the IRR method chooses the other, should generally be resolved in favour of the project with the higher NPV.