A Project Team Estimates That a Work Package Is Most

question 8

Multiple Choice

A project team estimates that a work package is most likely to have a duration of 10 days. However, under the worst possible conditions pessimistic) it will take 40 days, and if conditions are ideal optimistic) , it will take only 4 days. Using the PERT three-point estimation method, what is the expected time for this work package?


Definitions:

Externality

A side effect or consequence of an industrial or commercial activity that affects other parties without this being reflected in market prices.

National Defense

Governmental and military actions and policies aimed at protecting a country from external aggression, threats, and maintaining national security.

Patented Invention

A unique product or process that has been legally protected by a patent to give its inventor exclusive rights to use, make, or sell it for a certain period of time.

Tornado Siren

A warning system used in many communities to alert citizens about the imminent danger of a tornado.

Related Questions