What Are Possible Values for Earned Value EV), Planned Value

question 13

Multiple Choice

What are possible values for earned value EV) , planned value PV) , and actual cost AC) if a project has an SPI of 0.5 and a CPI of 2.0?

Understand the structure and functionalities of Access, including forms, subforms, and external file connections.
Master the concepts of file types, delimiting, and the role of common characters in data separation.
Gain knowledge on data sharing strategies across different platforms and formats.
Understand the concept of validity in psychological testing and its different types (predictive, concurrent, content).

Definitions:

Variable Costing

A costing method that includes only variable production costs—direct materials, direct labor, and variable manufacturing overhead—in the cost of goods sold and reports fixed overhead as an expense of the period.

Fixed Manufacturing Overhead

Indirect production costs that remain constant regardless of the level of goods or services produced.

Common Fixed Expenses

Expenses that remain constant in total over a relevant range of time or production volume and are shared by multiple business segments or products.

Contribution Margin

The amount remaining from sales revenue after variable expenses have been deducted, indicating how much revenue is contributing to cover fixed expenses and profit.

Related Questions