At zero direct labor hours in a flexible budget graph, the total budgeted cost line intersects the vertical axis at $20,000. At 10,000 direct labor hours, a horizontal line drawn from the total budgeted cost line intersects the vertical axis at $60,000. Fixed and variable costs may be expressed as: