A Customer Requests a New Order in a Period Where

question 16

Multiple Choice

A customer requests a new order in a period where there is inadequate material available in the available-to-promise (ATP) for that period, and the period is within the planning time fence. Which of the following is the best first course of action to take in such a situation?