question 19

Multiple Choice

The following two questions use the information in this MRP record. The lead time is 3 weeks.
 Week 12345 Gross requirements 6050607020 Scheduled receipts 100 Projected available 40903040 Net requirements Planned  order receipt Planned  order release 100\begin{array}{llllll}\text { Week } & 1 & 2 & 3 & 4 & 5 \\\text { Gross requirements } & 60 & 50 & 60 & 70 & 20 \\\text { Scheduled receipts } & & 100 & & &\\\text { Projected available }&40&90&30&&40\\\text { Net requirements Planned }\\\text { order receipt Planned }\\\text { order release } \quad100\end{array}
-The net requirement for week four is:


Definitions:

Client-Visits

The number of times clients go to a business or service provider's location within a specified period.

Planning Budget

An estimate of the income and expenditure for a set period of time, used for setting financial targets and objectives.

Wages and Salaries

Regular payments made by employers to employees in exchange for their work or services.

Activity Variance

The difference between planned or budgeted costs and the actual costs based on the level of activity or volume, used in variance analysis.

Related Questions