A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below. Activity times are in weeks. A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below. Activity times are in weeks.     Now assume that the times listed are only the expected times instead of being fixed times. Is the probability of being finished in fewer than 25 weeks more or less than 50%? A project network is shown below. Use a forward and a backward pass to determine the critical path, and then fill out the table below. Activity times are in weeks.     Now assume that the times listed are only the expected times instead of being fixed times. Is the probability of being finished in fewer than 25 weeks more or less than 50%? Now assume that the times listed are only the expected times instead of being fixed times. Is the probability of being finished in fewer than 25 weeks more or less than 50%?


Definitions:

Permanent Workforce

Employees who are considered permanent staff and have full-time employment contracts with benefits, as opposed to temporary or contractual staff.

Telecommuting

The practice of working from a remote location, outside of a traditional office environment, commonly from home, leveraging technology.

Distractions

Items or events that draw attention away from the task at hand, potentially reducing productivity or focus.

Productivity

The measurement of efficiency in which goods and services are created and delivered, often gauged by the output per unit of input.

Related Questions