Consider a Project That Has Been Modeled as Follows

question 21

Essay

Consider a project that has been modeled as follows: Consider a project that has been modeled as follows:   ​  a. Draw the PERT/CPM network for this project and determine project's expected completion time and its critical path. b. Can activities E and G be performed simultaneously without delaying the minimum project completion time? c. Can one person perform A, G, and I without delaying the project? d. By how much can activities G and L be delayed without delaying the entire project? e. How much would the project be delayed if activity G was delayed by 7 hours and activity L was delayed by 4 hours? Explain.
a.
Draw the PERT/CPM network for this project and determine project's expected completion time and its critical path.
b.
Can activities E and G be performed simultaneously without delaying the minimum project completion time?
c.
Can one person perform A, G, and I without delaying the project?
d.
By how much can activities G and L be delayed without delaying the entire project?
e.
How much would the project be delayed if activity G was delayed by 7 hours and activity L was delayed by 4 hours? Explain.


Definitions:

Industrial Development

The process of building up a country's capacity to process raw materials and manufacture goods for consumption or export.

Canadian Labor Law

The body of laws regulating employment, unions, and collective bargaining in Canada.

Decentralization

The distribution of decision-making powers and responsibilities away from a central authority to regional or local authorities or to individual units within an organization.

Business Flexibility

The ability of a company to adapt to changes in the market or industry, altering operations or structures to meet new challenges.

Related Questions