Five Jobs Are Ready for Processing at Time Zero Through

question 11

Multiple Choice

Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table.
 Job  Processing Time (days)   Due Date  A 618 B 314 C 49 D 519 E 211\begin{array} { | l | l | l | } \hline \text { Job } & \text { Processing Time (days) } & \text { Due Date } \\\hline \text { A } & 6 & 18 \\\hline \text { B } & 3 & 14 \\\hline \text { C } & 4 & 9 \\\hline \text { D } & 5 & 19 \\\hline \text { E } & 2 & 11 \\\hline\end{array}
Using the earliest due date (EDD) rule, the average flow time for the five jobs is _____.


Definitions:

Antidepressant Medications

Drugs prescribed to relieve symptoms of depression, anxiety disorders, seasonal affective disorder, and sometimes chronic pain conditions.

Psychotherapy

A method of treating mental health issues through talking with a psychotherapist to understand and manage behaviors, feelings, and thoughts.

Depression

A mood disorder featuring persistent feelings of sadness, loss, and hopelessness, often accompanied by a lack of interest in previously enjoyable activities.

Generalized Anxiety Disorder

A psychological disorder characterized by excessive, uncontrollable, and often irrational worry about everyday things, significantly impacting daily functioning.

Related Questions