Five Jobs Are Ready for Processing at Time Zero Through

question 9

Multiple Choice

Five jobs are ready for processing at time zero through a workstation. The details of the processing time and the due date of completion is provided in the following table.
 Job  Processing Time (days)   Due Date  A 511 B 616 C 319 D 410 E 29\begin{array} { | l | l | l | } \hline \text { Job } & \text { Processing Time (days) } & \text { Due Date } \\\hline \text { A } & 5 & 11 \\\hline \text { B } & 6 & 16 \\\hline \text { C } & 3 & 19 \\\hline \text { D } & 4 & 10 \\\hline \text { E } & 2 & 9 \\\hline\end{array}
Using the earliest due date (EDD) rule, the average lateness for the five jobs is:


Definitions:

Expected ROE

The projected return on equity for a future period, based on estimates of future earnings and shareholders' equity.

Risk-free Rate

An anticipated earning on an investment that is free from the danger of monetary loss, commonly illustrated by the return rate on state-issued securities.

Market-capitalization Rate

The combined value of all a company's shares currently on the market, found by taking the current price of one stock and multiplying it by the total number of shares available.

Expected Return

The anticipated average return of an investment over a specified period, based on historical data or statistical analysis.

Related Questions