Parent X Required 1 Each of Components Y and Z

question 7

Essay

Parent X required 1 each of components Y and Z. Both Y and Z are processed on work center 20 which has an available capacity of 40 hours. The setup time for component & is 1 hour and the run time 0.3 hours per piece. For component Z, setup time is 2 hours and the run time is 0.20 hours per piece. Calculate the number of Ys and Zs that can be processed.