Shop Order 7777 Is for 600 of Part #8900

question 12

Short Answer

Shop order 7777 is for 600 of part #8900. From the routing file, it is found that operation 20 is done on work center 300. The setup time is 3.5 hours, and run time is 0.233 hours per piece. What is the required capacity on work center 300 for shop order 7777.