Define and calculate slack time within a project schedule.
Describe the purpose and mechanics of the Program Evaluation and Review Technique (PERT) including expected completion times and variance calculations.
Distinguish between the Critical Path Method (CPM) and PERT, including their purposes and methods of calculation.
Understand the construction and analysis of network diagrams, including the calculation of earliest and latest start times, and total project duration.

Definitions:

Dow Jones

A reference to either the Dow Jones Industrial Average (DJIA), a stock market index of 30 prominent companies in the U.S., or the company Dow Jones & Company, known for its financial market indices and news.

Industrial Average

A stock market index that measures the performance of a sector of the economy, typically composed of leading companies in that sector.

Price-Weighted

Refers to a stock market index in which each company's stock influences the index in proportion to its price per share.

Money Market

A segment of the financial market in which short-term financial instruments, such as Treasury bills and commercial paper, are traded.

Related Questions