The Amount of Drying Time for the Paint Applied to a Plastic

question 15

True/False

The amount of drying time for the paint applied to a plastic component part is thought to be uniformly distributed between 30 and 60 minutes. Currently, the automated process selects the part from the drying bin after the part has been there for 50 minutes. Based on this, the probability that a part selected will not be dry is approximately 0.33.