In Setting Up a Kanban Control System You Need to Determine

question 3

Multiple Choice

In setting up a Kanban control system you need to determine the number of Kanban card sets needed.If the expected demand during lead time is 25 per hour, the safety stock is 20% of the demand during lead time, the container size is 5, and the lead time to replenish an order is 5 hours, what is the number of Kanban card sets needed?