At a Production Level of 5,600 Units a Project Has

question 117

Multiple Choice

At a production level of 5,600 units a project has total costs of $89,000. The variable cost per unit is $11.20. What is the amount of the total fixed costs if the production level is increased to 6,100
Units without increasing the total fixed assets?