Assume that an assembly line has three tasks that must be completed (in order, A, B, and C) . The tasks have processing times of 12, 15, and 10 minutes per unit, respectively. If the assembly line operates for 480 minutes per day with a desired output of 50 units per day, what is assembly line efficiency?
Nearest 0.01%
Rounding to the closest one-hundredth of a percent, often used in financial calculations to ensure precision.
Terminating Decimal
A decimal fraction that comes to an end or has a finite number of digits after the decimal point.
Five-Figure Accuracy
A level of precision where a numerical value is rounded to the nearest ten-thousandth place, representing the first five significant digits.
Terminating Decimal
A decimal fraction that has a finite number of digits after the decimal point.
Q8: Customer orders, in a flow management context,
Q16: Assume that customer arrivals at a small
Q37: Mungo Pet Supplies makes cat trees for
Q54: The FCFS job shop dispatch rule has
Q71: CAM, in the context of manufacturing flexibility,
Q73: A positive error implies that a forecast
Q76: The average inventory level in the EOQ
Q120: Lean thinking is best described as a(n)?<br>A)
Q125: Assume that customer arrivals at a ticket
Q131: For a single server, single queue system