Multiple Choice

A project has four activities: A, B, C, and D. The amount spent on each activity to date is $22K, $14K, $12K, and $28K respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the cost variance for the project?


Definitions:

Economic Differences

Variations in wealth, income, or economic structures between individuals, regions, or countries.

James Blaine

James Blaine was a prominent American politician and statesman in the late 19th century, who served as Speaker of the House, a U.S. Senator from Maine, and Secretary of State, and was the Republican nominee for president in 1884.

Civil War

A war between citizens of the same country, often fought over issues of political power, territorial control, or social inequalities.

Voter Participation

The extent to which eligible voters participate in elections, a crucial aspect of democratic governance.

Related Questions