You have collected the data for a time-cost CPM scheduling model analysis. The time is in days and the project "direct costs" are given here. The indirect costs for the project are determined on a daily duration basis. If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100.
At what day do we achieve the lowest total project cost (i.e., direct plus indirect costs) ?
Primary Datum
A reference point, axis, or plane from which dimensions are measured or a baseline for the construction of geometric features in drawings.
Geometric Tolerances
The limits of allowable variation in the shape and size of a part's geometry, including its form, orientation, and location, specified in engineering drawings.
Straightness
A condition where an element or line maintains a consistent path without deviation, typically applied in manufacturing to ensure parts are within specified tolerances.
Flatness
A geometric tolerance that describes how flat a surface must be within specified limits.
Q5: Using the probability approach to determine an
Q36: Labor cost and machine hours are ignored
Q41: The first step in balancing an assembly
Q46: Smaller transfer batches give lower work-in-process inventory
Q47: In a concurrent engineering approach to product
Q48: You time someone completing a single task
Q55: Various financial data for SunPath Manufacturing for
Q59: There is little to be gained by
Q64: According to the theory of constraints, which
Q105: Breakthrough projects are those that provide fundamental