A Project Has Four Activities: A, B, C, and D

question 7

Multiple Choice

A project has four activities: A, B, C, and D. The amount spent on each activity to date is $22K, $14K, $12K, and $28K respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the BCWS for Activity A?


Definitions:

Overt Abuse

Explicit and observable acts of physical, emotional, or other forms of abuse against an individual.

Child Neglect

A form of child abuse involving the failure of a parent or caretaker to provide necessary food, clothing, shelter, medical care, or supervision to the degree that the child's health, safety, and well-being are threatened with harm.

Secondary Prevention

Efforts aimed at early detection and intervention to halt the progression of a disease or condition at an early stage.

Immunizing

The process of making an individual immune to a disease, typically by vaccination, to reduce their susceptibility to specific infectious diseases.

Related Questions