In a Net Change MRP Program, a Change in One

question 23

True/False

In a net change MRP program, a change in one item will result in a completely new inventory plan and schedule for every item in the master production schedule.


Definitions:

Regulatory Scheme

A system of regulations established by governments or regulatory bodies to control or govern specific activities, industries, or behaviors.

ISO 14001

An international standard that outlines the requirements for an effective environmental management system (EMS).

American National Standards Institute

An organization that oversees the creation, promulgation, and use of thousands of norms and guidelines that directly impact businesses in nearly every sector.

Preconstruction Review

An assessment process conducted before the start of a construction project to ensure compliance with relevant codes and regulations.