Definitions:

CPM Networks

CPM Networks, standing for Critical Path Method Networks, are project management tools used to schedule, organize, and coordinate tasks within a project.

Project Crashing

A project management technique used to reduce the project duration without altering the scope of the project, by adding resources to critical path tasks.

Crash Cost

Additional costs incurred to complete a project much faster than originally planned, often leading to increased expenses.

Normal Duration

The standard, expected amount of time taken to complete a task or process under normal conditions.