Examlex
Larry's Wickets, Inc. is producing two types of products: A and B. Both are produced at the same machining operation. Because of demand uncertainties, the operations manager obtained three demand forecasts (pessimistic, expected, and optimistic). The demand forecasts, batch sizes (units/batch), processing times (hr/unit), and setup times (hr/batch) follow.
The machines operate on two 8-hour shifts, 5 days per week, and 50 weeks per year. The manager wants to maintain a 20 percent capacity cushion.
a. What is the minimum number of hours required of the machining equipment for the next year?
b. How many hours of capacity can the company expect from each machine?
c. What is the minimum number of machines needed (assuming no reliance on short-term options)?
d. What is the maximum number of machines needed (assuming no reliance on short-term options)?
Natural Log
A logarithm to the base e (where e is approximately 2.71828), used extensively in mathematical, economic, and scientific applications.
Risk Averter
An individual or entity that prefers to avoid uncertainty and potential losses when making investment or financial decisions.
Expected Value
In probability theory, it is the weighted average of all possible values of a random variable, with weights being the probabilities of each outcome.
Natural Log
The logarithm to the base e, where e is an irrational and transcendental constant approximately equal to 2.71828.
Q72: Process capability determines whether a process is
Q93: What is the crashing cost per week
Q97: _ is a continuous, systematic procedure that
Q99: Which of these is not one of
Q146: All forms of benchmarking are best applied
Q147: Which of these benchmarking metrics is not
Q148: Bias error causes the greatest disruption to
Q149: Use the information in Scenario 2.1. What
Q152: MKS Inc., produces meter sticks that have
Q161: _ is based on comparison of processes