Examlex

Solved

Table 7.4 -Using Table 7.4, What Is the Minimum Number of Activities

question 98

Multiple Choice

Table 7.4
Table 7.4    -Using Table 7.4, what is the minimum number of activities that would have to be crashed to cause a decrease in the project's earliest completion date? A)  one activity B)  two activities C)  three activities D)  four or more activities
-Using Table 7.4, what is the minimum number of activities that would have to be crashed to cause a decrease in the project's earliest completion date?