Table 7.5 -Using Table 7.5, How Many Days Can Activity C Be

question 124

Multiple Choice

Table 7.5
Table 7.5    -Using Table 7.5, how many days can activity C be delayed without changing the whole project's earliest completion time? A)  0 days B)  2 days C)  5 days D)  7 days
-Using Table 7.5, how many days can activity C be delayed without changing the whole project's earliest completion time?