Table 7.8
Table 7.8    -Using Table 7.8, what is the minimum crashing cost to finish this project in 18 days? A)  $3,450 B)  $850 C)  $1,150 D)  $1,500
-Using Table 7.8, what is the minimum crashing cost to finish this project in 18 days?