Table 7.2 -Using Table 7.2, If the Expected Times for Activities A

question 94

Multiple Choice

Table 7.2
Table 7.2    -Using Table 7.2, if the expected times for activities A, G, and H increased by 2, 3, and 4 weeks, respectively, by how many weeks would the project's earliest expected time of completion increase? A)  fewer than or equal to 2 weeks B)  greater than 2 weeks but fewer than or equal to 4 weeks C)  greater than 4 weeks but fewer than or equal to 6 weeks D)  greater than 6 weeks
-Using Table 7.2, if the expected times for activities A, G, and H increased by 2, 3, and 4 weeks, respectively, by how many weeks would the project's earliest expected time of completion increase?


Definitions:

Confidential Information

Sensitive information that is not public knowledge and is protected by law or agreement, requiring it to be kept secret.

Client Confidentiality

The ethical obligation of professionals, especially in law, to keep information related to a client secret and secure.

Attorney-Client Privilege

A legal principle that keeps communications between an attorney and their client confidential, encouraging open and honest discussion.

Threats of Death

The act of implying or directly stating the intention to kill someone, which can be a criminal offense.

Related Questions