Table 7.14 You Are Responsible for Managing a Project with the Following

question 116

Multiple Choice

Table 7.14
You are responsible for managing a project with the following activities (times are given in weeks) .
Table 7.14 You are responsible for managing a project with the following activities (times are given in weeks) .    -Using Table 7.14, what is the probability that the project will take 16 or more weeks to complete? A)  less than or equal to 20% B)  greater than 20% but less than or equal to 25% C)  greater than 25% but less than or equal to 30% D)  greater than 30%
-Using Table 7.14, what is the probability that the project will take 16 or more weeks to complete?