Following Are Four Sets of Most Optimistic, Most Likely, and Most

question 81

Multiple Choice

Following are four sets of most optimistic, most likely, and most pessimistic times (in weeks) for an activity. Which one of the four sets will have a mean estimated time equal to the most likely time?