Table 7.2    -Using Table 7.2, what is the earliest expected time of completion of the whole project? A)  fewer than or equal to 19 weeks B)  greater than 19 but fewer than or equal to 21 weeks C)  greater than 21 but fewer than or equal to 24 weeks D)  greater than 24 weeks
-Using Table 7.2, what is the earliest expected time of completion of the whole project?