Table 7.13
All activity times for the project are in weeks.
Table 7.13 All activity times for the project are in weeks.    -Using Table 7.13, what is the critical path of this project? A)  A-D-H B)  C-E-H C)  B-F-G-H D)  C-E-H and B-F-G-H are both critical.
-Using Table 7.13, what is the critical path of this project?