Scenario 9.11 Demand = 50,000 Units/week

question 146

Multiple Choice

Scenario 9.11
Demand = 50,000 units/week
Standard deviation of weekly demand = 15,000 units
Average lead time = 8 weeks
Standard deviation of lead time: 3 weeks
Cycle-service level = 80%
A continuous review system is used to control inventory.
-Use the information in Scenario 9.11. What reorder point should the firm use for this product?