Table 10.4
Gable Express Co. provides delivery service seven days a week. The daily requirements (in workers) are estimated as follows:
Each worker is required to work five days per week, and each must have two consecutive days off.
-Use the information in Table 10.4. How much total slack will be generated from the schedule?