Use the following partially completed MRP record to answer the question. Use the following partially completed MRP record to answer the question.   What are the quantities of planned order releases for item XYZ for the first six weeks (weeks 1, 2, 3, 4, 5, and 6) ? A)  20, 30, 0, 40, 20, 0 B)  35, 0, 60, 0, 0, 0 C)  5, 30, 0, 40, 20, 0 D)  35, 0, 0, 40, 20, 0