You Are About to Undertake the Manufacture of a Labor-Intensive

question 77

Essay

You are about to undertake the manufacture of a labor-intensive electronics component. The first unit took 300 hours. You are not sure whether the learning curve is 70% or 80%. The initial phase of the contract calls for 6 of these components.
(a) How much time will it take to complete all six at 70% learning?
(b) How much time will it take to complete all six at 80% learning?


Definitions:

Marginal Revenue Curve

A graphical representation showing how marginal revenue changes as output level changes.

Competitive Industry

An industry characterized by many firms offering similar products where no single firm can influence the market price.

Monopolistic Industry

An industry characterized by the domination of one firm which controls the majority of the market share and can influence price and competition.

Municipal Stadium Authority

A governmental or quasi-governmental entity responsible for the financing, building, and operation of a stadium or arena in a municipality.

Related Questions