A Defense Contractor Has Just Started Producing Engines for a New

question 95

Multiple Choice

A defense contractor has just started producing engines for a new government contract. The first engine took 800 hours to produce. If the learning curve is 80%, approximately how long will it take to produce the first 20 engines?