A Linear Programming Problem Has Three Constraints, Plus Nonnegativity Constraints

question 75

Multiple Choice

A linear programming problem has three constraints, plus nonnegativity constraints on X and Y. The constraints are: 2X + 10Y ≤ 100; 4X + 6Y ≤ 120; 3X + 3Y ≤ 90. What is the largest quantity of X that can be made without violating any of these constraints?

Understand the prevalence and effects of fetal alcohol spectrum disorders in children.
Understand the concept and factors involved in a home birth.
Differentiate between preterm and small for date babies.
Identify the effects of alcohol use during pregnancy.

Definitions:

Deferred Tax Asset

A tax relief that results from over-payment or advance payment of taxes, which can be used to reduce a company's future tax liability.

Prepaid Asset

Expenses paid in advance for goods or services to be received in the future, which are recorded as assets until they are used or consumed.

Taxable Income

The amount of income subject to taxes, calculated by adjusting gross income for deductions, exemptions, and allowances, according to tax laws.

Deferred Income Tax Asset

A balance sheet item that represents taxes paid or carried forward but not yet realized on the income statement.

Related Questions