The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants-Charlie, Gerald, Johnny, and Rick-to complete any of the four projects, as follows:
(a) What is the total number of hours required by the following arbitrary assignment?
Charlie→B; Gerald→A; Johnny→C; Rick→D
(b) What is the optimal assignment of consultants to projects? (Use the assignment method.)
(c) For the optimal schedule, what is the total number of hours it will take these consultants to complete these projects?
Fair Adjustment
An equitable modification or change made to correct or improve a situation, ensuring fairness to all parties involved.
Professional Tone
Refers to the formal or business-like language used in corporate or professional communication.
Indirect Approach
A communication strategy where the main point or message is not presented first but instead is built up to through explanations, background information, or related details.
Pelvic Cavity
The body cavity located within the pelvis, housing organs such as the bladder, reproductive organs, and rectum.
Q8: Century Digital Phone advertises phone battery life
Q29: Reduced inventory levels and faster response to
Q48: A manufacturer of industrial seafood processing equipment
Q55: Find the minimum cost solution for the
Q74: Cross-training is a common JIT layout tactic
Q79: A(n) _ is a graphical means of
Q80: A Gantt load chart shows the loading
Q104: Preventive maintenance is reactive.
Q116: A printing company estimates that it will
Q124: _ software replaces paper-based transaction records with