Develop a Solution for the Following Line Balancing Problem, Allowing

question 154

Essay

Develop a solution for the following line balancing problem, allowing a cycle time of 5 minutes.
(a) Draw the precedence diagram for the set of tasks.
(b) Calculate the theoretical minimum number of workstations.
(c) Balance this line using the longest task time heuristic.
(d) What tasks are assigned to which stations?
(e) Does the solution have the minimum number of stations? Explain.
(f) How much idle time is there, summed over all workstations?
(g) What is the efficiency of this line?
Develop a solution for the following line balancing problem, allowing a cycle time of 5 minutes. (a) Draw the precedence diagram for the set of tasks. (b) Calculate the theoretical minimum number of workstations. (c) Balance this line using the longest task time heuristic. (d) What tasks are assigned to which stations? (e) Does the solution have the minimum number of stations? Explain. (f) How much idle time is there, summed over all workstations? (g) What is the efficiency of this line?


Definitions:

Conversion Costs

The combined costs of direct labor and manufacturing overhead, representing the expenses to convert raw materials into finished goods.

Cost Per Equivalent Unit

A calculation used in process costing, dividing the total cost by the number of units produced to determine the cost per unit.

Conversion Costs

Costs required to convert raw materials into finished products, usually including direct labor and manufacturing overhead.

Conversion Costs

The costs required to convert raw materials into finished goods, which typically include direct labor and manufacturing overhead.

Related Questions