The Critical Path for the Network Activities Shown Below Is

question 130

Multiple Choice

The critical path for the network activities shown below is ________ with duration ________. The critical path for the network activities shown below is ________ with duration ________.   A)  A-D-E; 11 B)  B-E; 7 C)  B-D-E; 13 D)  A-C-E; 6 E)  B-C-E; 8