The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network.
The network below represents a project being analyzed by the critical path method. Activity durations are indicated on the network.    (a) Identify the activities on the critical path. (b) What is the duration of the critical path? (c) Calculate the amount of slack time at activity H. (d) If activity I were delayed by ten time units, what would be the impact on the project duration? (a) Identify the activities on the critical path.
(b) What is the duration of the critical path?
(c) Calculate the amount of slack time at activity H.
(d) If activity I were delayed by ten time units, what would be the impact on the project duration?


Definitions:

Liabilities

Liabilities are financial obligations a company owes to external parties, such as loans, accounts payable, and mortgages.

Accrual

An accounting method that records revenues and expenses when they are incurred, regardless of when cash is exchanged.

Accrual

The accounting method that records revenues and expenses when they are incurred, regardless of when cash transactions occur.

Accounting Cycle

The process used by entities to analyze and record transactions, adjust the records at the end of the period, prepare financial statements, and prepare the records for the next cycle.

Related Questions