First cost of a construction project depends on weather. Historical weather data shows that in the fall weather is warm 20% of the time, it is cold 30% of the time and it is somewhat in between 50% of the time. During warm weather, first cost is expected to be $225 000, during cold weather $295 000 and $250 000 in between. What is the expected value of the first cost?