An activity's normal time and cost are 10 and $120, respectively. Its estimated crash time and cost are 7 and $180, respectively. What is this activity's crash cost per time unit?


Definitions:

Environmental Context

The physical, social, and cultural settings that surround and influence an individual or event, affecting how they are perceived or behave.

Emotions and Memory

The interaction between the psychological states of feelings and the cognitive system responsible for encoding, storing, and retrieving information.

Motivations on Perception

Refers to how internal drives and desires influence one's interpretation of sensory information.

Impact of Emotion

The effect that emotions have on human processes and behaviors, including decision making, creativity, relationships, and physical health.