Phase Estimating Is Used When a Project Cannot Be Rigorously

question 3

True/False

Phase estimating is used when a project cannot be rigorously defined because of the uncertainty of design or the final product.


Definitions:

Confidence Interval

A breadth of values, taken from statistical examination of a sample, that aims to envelop the value of an unrevealed population trait.

Standard Deviation

Standard deviation is a measure of the amount of variation or dispersion in a set of values, indicating how much the individual data points diverge from the mean value.

Sample Mean

The average value calculated from a subset of a population.

Confidence Level

The probability that the values of a parameter lie within a specified range of values, indicating the reliability of an estimate.