The most detailed element in the hierarchical breakdown of the project work to be accomplished is known as the __________.


Definitions:

Capital Budget

A budgeting process that entails the evaluation and planning of expenditures for projects and investments that are significant in scope and that will be amortized over several years.

Stock Split

A corporate action in which a company divides its existing shares into multiple shares to boost the liquidity of the shares, although the market capitalization remains the same.

Total Market Value

The combined value of all shares of stock, bonds, or other securities issued by a company, calculated by multiplying the current price per share by the total number of shares outstanding.

Increased Liquidity

The state or condition of having more cash or easily convertible into cash assets, making it easier to meet short-term obligations.