Scrum Uses a Series of Coordinated Meetings to Manage the Development

question 50

Multiple Choice

Scrum uses a series of coordinated meetings to manage the development process. Which of the following is held at the start of each sprint? During this meeting the product owner and development team negotiate which product backlog items the team will attempt during the next sprint.